How to run a weekly site coordination meeting
The weekly coordination meeting is where a project's problems between parties get solved — or carried forward for another week. Here is how to keep it short, keep it useful and make sure what is agreed actually happens, with a free one-page agenda to run it from.
By Space Team·Updated
What the meeting is for
A site coordination meeting exists to solve the problems that sit between parties: work blocked on an answer, a drawing that has changed, a decision only the client can make, two agencies who need the same wall in the same week. Anything one party can sort out on its own does not need the meeting.
What it is not is a status update read out round the table. If each agency spends five minutes saying what it did last week, an eight-party meeting is forty minutes old before a single problem is discussed. Progress can be collected before the meeting; the meeting is for what nobody can fix alone.
Who should attend
- The PMC, who usually chairs. Where there is no PMC, the architect or the client's project manager.
- The architect, for design questions and drawing issues.
- Consultants — structural, MEP, electrical — when their discipline is on the agenda. Not every week by default.
- The contractors and agencies with work in the next two weeks. An agency that starts next month can join next month.
- The client, for the items that need their decision. Schedule those together so they can join for that part rather than the whole meeting.
Small beats complete. Every extra person who is there "just in case" makes the meeting longer for everyone who needs to be there.
Before the meeting
Most of a good meeting happens the day before. Circulate the agenda at least 24 hours ahead, with:
- The open actions from the last minutes, each with its owner.
- Open RFIs, oldest first, and which work each one is holding up.
- Drawings issued or revised since the last meeting.
- The decisions the client is being asked to make.
Ask each agency to bring two things only: its look-ahead for the next two weeks, and anything blocking it.
A 45-minute agenda
Times will vary with the size of the project. The order matters more than the minutes: unblock work first, then look ahead, then read back.
- 0–5 min · Last meeting
- Confirm the previous minutes. Run through open actions — done, not done, new date.
- 5–15 min · Blockers and RFIs
- Open RFIs, oldest first. For each one: who owes the answer, and by when. Anything blocking work this week comes first.
- 15–25 min · Drawings
- Revisions issued since last week, and anything still waiting to be revised. Confirm everyone is working from the current revision.
- 25–35 min · Client decisions
- Each decision with its options and what is waiting on it. The client joins for this block if not for the rest.
- 35–42 min · Two-week look-ahead
- What each agency starts in the next two weeks, and where one agency's work depends on another's.
- 42–45 min · Read-back
- Read back every action with its owner and due date, and confirm the next meeting.
Chairing it
- Walk the items, not the people. Going round the table invites status reports; going down the agenda keeps the meeting on problems.
- End every item with a decision, an owner and a date — or with an explicit "carried forward" and the reason.
- Take detail offline. When two parties need twenty minutes on one junction, agree who meets whom and when, and move on.
- Let people speak the language they are comfortable in. On many Indian sites one meeting runs in Gujarati, Hindi and English. The chair's job is to restate each decision in one language for the minutes, so nothing is lost in translation.
- Walk to it when the item is a place. Five minutes standing at the problem saves fifteen describing it.
After the meeting
- Issue the minutes within 24 hours, while the meeting is fresh enough for people to correct them. Our construction MoM template is laid out for exactly this meeting.
- Raise the RFIs the meeting identified, each directed to one party with a needed-by date. See our guide to writing an RFI.
- Update the drawing register for any revision the meeting asked for, and issue it with a transmittal.
- Ask each agency to acknowledge its actions.
- Chase the open actions before the next meeting, not at it.
A worked example
A weekly coordination meeting on a residential project: four people, three languages, 42 minutes. Here is what was said, which part of the agenda it belongs to, what the meeting turned it into and what happened next.
- 01
Blockers and RFIs
Electrical Consultant · Hindi
“Plumbing shaft 150 mm shift ho sakta hai, lekin drawing update karni padegi.”
The plumbing shaft can move 150 mm, but the drawing needs updating.
- The meeting recorded
- Plumbing shaft shift approved subject to revised drawing.
- Then
- Architect answered Q-014: “Shift approved by 150 mm. Update the drawing before execution.”
- 02
Drawings issued and pending
Architect · Gujarati
“Electrical consultant Friday sudhi revised kitchen layout issue kari deshe.”
Electrical consultant will issue the revised kitchen layout by Friday.
- The meeting recorded
- Task: Revise kitchen electrical points · Electrical Consultant · due Friday
- Then
- A-602-E-104 reissued as V9 on 15 Sep 2026.
- 03
Client decisions
PMC · English
Living room flooring still needs client approval.
- The meeting recorded
- Task: Confirm living room flooring approval · Client · due Thursday
- Then
- D-007 recorded: Onyx.
- 04
Client decisions
Client · Gujarati
“Sofa kaya type na levana che e nakki karvanu baki che.”
We still need to decide the type of sofas.
- The meeting recorded
- Decision: Sofa type for living room · Client + Architect
- Then
- Still open — carried forward to the next meeting.
Common mistakes
- A status report from every party before any problem is discussed.
- Everyone invited to everything.
- No agenda, so the loudest item wins.
- Decisions with no owner or date.
- The client sitting through an hour of site detail for one decision.
- Minutes written days later, from memory.
- The same items on the agenda every week, with nothing changing.
From meeting notes to follow-up that is already organised
However well a meeting runs, someone still has to turn it into minutes and work afterwards. Space does that part from the meeting itself.
- Record the meeting in Space, with everyone speaking whatever language they are comfortable in.
- The transcript keeps each speaker separate, in the language spoken, with an English translation alongside.
- Space prepares a summary and the Minutes of Meeting, and suggests the tasks, queries and decisions that came out of it — each quoting the line it came from.
- A person reviews every suggestion and decides whether it becomes work. Nothing is created automatically.
- Months later, the meeting is still there to show why something changed.
Questions
- How long should a site coordination meeting be?
- Around 45 minutes to an hour for most projects. If it regularly runs longer, the usual causes are status updates round the table, too many attendees or detail that should have been taken offline.
- Who chairs the site coordination meeting?
- Usually the PMC. On projects without a PMC, the architect or the client's project manager chairs. The chair also issues the minutes.
- How often should coordination meetings be held?
- Weekly is the norm during construction. Early design stages and quiet periods may need them less often; intense phases such as services coordination sometimes need two a week.
- What is the difference between a coordination meeting and a progress meeting?
- A progress meeting reviews where the work stands against the programme. A coordination meeting resolves problems between parties — blockers, RFIs, drawings, decisions. Many projects combine them; if you do, keep the progress part short.
- Should the client attend site coordination meetings?
- For the decisions that need them, yes. Group the client's items into one block of the agenda so they can join for that part rather than the whole meeting.
Meetings & AI
Run the meeting. Space prepares the minutes and suggests the follow-up, for your team to review.